Skip to Main Content
Alert
Beginning Wednesday, January 7, 2026, water crews will conduct a fire hydrant leak repair at Summit Avenue and 10th Street. Two northbound lanes on Summit Avenue between Texas Street and 7th Street will be closed during repairs. Work is expected to be completed by the weekend.

Calhoun St (Deco 969) Crane Closure

May 11,2023


Reposted from the City of Fort Worth

From Thursday, June 8 – Monday, June 12, a five-day crane closure will be taking place downtown for Calhoun Street between 7th Street and 12th Street between 9:00 AM – 6:00 AM for the removal of an existing tower crane currently in place at this site via an additional 600-ton crane. Travel lanes will be completely closed between 7th Street and 12th Street. The traffic control plan is attached and the contractor is notifying stakeholders.