Weatherford Street and Belknap Street Bridge Improvements

July 5,2017


Beginning July 17, bridge approaches and damaged concrete panels will be replaced on Weatherford and Belknap Streets. Traffic will be reduced to one lane each direction during the construction. Please follow all posted notices and expect delays during construction. Improvements are expected to be complete by the end of August.

Update - August 9, 2017

Traffic has been moved to the left hand lanes on both Belknap Street and Weatherford Street. This project is on schedule, and is expected to complete in 6 weeks.

Contact

Tariqul Islam
Project Manager
City of Fort Worth
Transportation & Public Works Department
817-392-2486